Monitoring and Investigation in One Record

When equipment trips without explanation, most facilities call for a power quality survey: an engineer connects a portable analyzer, records for a few weeks, and hopes the problem repeats with the triggers set to catch it. The survey exists because the meter in the switchgear or switchboard keeps only summaries and short windows around its triggers, so the waveform of the trip is gone. A permanent Continuous Point-on-Wave (CPOW) installation brings the two together: it stays in place like the meter, records in more detail than the survey by keeping every waveform, and so has the trip on record before anyone asks about it.

Side by Side

Portable analyzerInstalled power quality meterCPOW with edge analysis
InstallationTemporary, for up to a monthPermanentPermanent
Between eventsLogs RMS summaries at set intervalsLogs RMS summaries at set intervalsRecords every sample of every channel
WaveformsCaptures short windows around triggersCaptures short windows around triggersRecords all of them
A disturbance below the thresholdLogs a summary value, no waveformLogs a summary value, no waveformRecords it in full
A question nobody asked in advanceAnswers only from what it capturedAnswers only from what it capturedAnswers from the full record
AnalysisA specialist works through the data after the surveyVendor software generates reports and alarmsRuns at the edge as data arrives; AI-guided diagnosis cites the waveform
When a problem appearsAn engineer connects it and waits for a repeatRaises an alarm and logs a summaryAlready holds the waveform from before, during, and after

Thirty Days of Survey, No Waveform

In a commercial building with recurring blown elevator fuses, standard power quality instruments ran for 30 days. Statistically binning their interval averages of power and current against elevator activity narrowed the cause to elevator operation. Averages, however, cannot show the inrush currents themselves or how they lined up in time, and no waveform was recorded at the moments the fuses opened, so the cause stayed an inference. A permanent continuous record would have held every elevator start, including the ones that blew fuses, with each inrush and its timing in view.

What a Permanent Record Changes

Where a contract or tariff names a certified IEC 61000-4-30 Class A instrument, that instrument remains the reference for the measurement it certifies. Installed beside it, the CPOW record holds the waveforms behind what it reports.

Where to Start

Install on the circuits that cost the most when they misbehave: feeders to sensitive production equipment, the UPS and transfer path, and loads that trip without explanation.

The CPOW primer explains how continuous capture works and what to ask of any recorder; the power quality primer covers the disturbances themselves and what they cost.

Go Back to Any Moment in the Control Room

Work with a live continuous waveform record from our lab, and open any cycle it holds.